Egypt's first modern solar thermal large-scale facility is almost complete (Desertec reference proj)

Printer-friendly format Printer-friendly format
Printer-friendly format Email this thread to a friend
Printer-friendly format Bookmark this thread
This topic is archived.
Home » Discuss » Topic Forums » Environment/Energy Donate to DU
 
OKIsItJustMe Donating Member (1000+ posts) Send PM | Profile | Ignore Fri Apr-16-10 08:52 AM
Original message
Egypt's first modern solar thermal large-scale facility is almost complete (Desertec reference proj)
http://www.solarmillennium.de/Press/Press_Releases/Solar_Millennium_AG__The_assembly_of_all_parabolic_trough_collectors_in_Egypt_has_been_completed_,lang2,50,1822.html
2010-04-15

Solar Millennium AG: The assembly of all parabolic trough collectors in Egypt has been completed

  • Egypt's first modern solar thermal large-scale facility is almost complete
  • Power plant will use both solar energy and natural gas in hybrid operation
  • Reference project for the entire region: Solar thermal power generation in North Africa as first sign for the feasibility of the DESERTEC concept
Erlangen/Cologne/Kuraymat (Egypt), 15 April 2010 The final collector unit for Egypt's first ever solar thermal large-scale facility has been assembled and installed in the solar field at Egypt's Kuraymat project site, some 100 km south of Cairo. The technology for the parabolic trough solar field comes from Flagsol GmbH in Cologne, a technology company jointly owned by the Erlangen based Solar Millennium AG (ISIN DE0007218406) and Ferrostaal AG, based in Essen. The engineers in Cologne designed the solar field and supplied the controls for the solar field. Moreover, the international technology company is responsible for supplying important key components, especially the parabolic mirrors and absorber pipes. The construction and commissioning of the solar field is taking place in cooperation with the Egyptian company Orascom Construction Industries.

Overall, almost 2,000 collectors with mirrors covering 130,000 square metres have been assembled and installed in the solar field. Each unit is 12 metres long and 6 metres wide. The collectors were assembled by specialists in the purpose-built assembly hall before their optical precision was controlled by a photogrammetric device. The collectors were then taken to the solar field where the last absorber pipes and controls are being installed. At the same time, the first rows of collectors are already being commissioned. Klaas Rühmann, Flagsol's project manager in charge of the project explains, "We thus initially test the basic functionalities and the controls for tracking the sun".

The heat transfer circuit for the entire solar field should also be commissioned successively starting in April. This involves a heat transfer medium, which flows through the absorber pipes in the focal line of the solar collectors and which is heated up to about 400 degrees Celsius by the concentrated solar radiation. This thermal energy will be fed into the power station unit as soon as this unit has been completed by the company in charge. Commissioning of the entire power plant is scheduled to take place in autumn 2010.

The hybrid power plant with 150 Megawatt capacity uses both natural gas and solar energy to generate electricity. The power plant is being built on behalf of the Egyptian New and Renewable Energy Authority NREA. The hybrid power plant was put out to international tender and the total cost will amount to more than € 250 million, about 30% of which is allocated to the realisation of the solar field. Flagsol and Orascom Construction Industries will run the solar part of the power plant for two years after commissioning, before it is finally handed over to the owners. The Global Environment Facility (GEF) has granted a USD 50 million subsidy for the solar field due to the project's exemplary status.

Rühmann comments on the progress of the construction work, "Our team is keeping good time. Cooperation with our Egyptian partner has worked very well. All employees are happy to have played a part in enabling this large solar plant. It is a reference project for the entire region. Commissioning of the overall power plant can begin as soon as the conventional power block has also been completed."

Dr. Thomas Thaufelder, Managing Director at Flagsol comments, "Of course we are quite proud that our pioneering work has been able to make a mark in Egypt - also in view of the implementation of the DESERTEC concept. An important goal of the international industry initiative Dii is to generate solar power for use in the North African states before it is exported to Europe. This initial project can soon demonstrate the successful implementation of this goal."


Please find http://www.solarmillennium.de/Technology/Reference_Projects/Hybrid_Power_Plant__Egypt_/Solar_Power_for_Egypt__Flagsol_Supplies_the_Country_s_First_Solar_Field_,lang2,183.html">further information on the project here.

...
Printer Friendly | Permalink |  | Top

Home » Discuss » Topic Forums » Environment/Energy Donate to DU

Powered by DCForum+ Version 1.1 Copyright 1997-2002 DCScripts.com
Software has been extensively modified by the DU administrators


Important Notices: By participating on this discussion board, visitors agree to abide by the rules outlined on our Rules page. Messages posted on the Democratic Underground Discussion Forums are the opinions of the individuals who post them, and do not necessarily represent the opinions of Democratic Underground, LLC.

Home  |  Discussion Forums  |  Journals |  Store  |  Donate

About DU  |  Contact Us  |  Privacy Policy

Got a message for Democratic Underground? Click here to send us a message.

© 2001 - 2011 Democratic Underground, LLC