Finally, its happening.
The Associated Press and Burlington Free Press are reporting that Vermont Senate leaders are now calling for a vote on whether or not Vermont Yankee nuclear power plant should be allowed to operate beyond 2012 when its license expires.
The plant was originally designed to last 40 years, and the license expires at this time. There have been numerous safety problems with the plant, including leakage of radioactive materials, fires, and coolant leaks. Recently an inspection of the plant found over 60 problems, most of which have not been addressed. Additionally, representatives from Entergy, the owners of the plant have been condemned for providing false information to government officials and an investigation is underway.
The Vermont Legislature must approve an extension of the license.
Senate leaders indicated the vote could take place as early as next week.
on edit, partial list of problems at Vermont Yankee in recent years:
radioactive fuel rods lost for 3 months (April 04);
transformer fire (June 04);
cracks discovered in the steam dryer (2004, 2005 & 2008);
hot shipment that left VY four times more radioactive than allowable federal limits (August 06);
cooling tower collapse and automatic shutdown of reactor due to stuck valve (August 07);
malfunctioning crane drops cask of high-level spent fuel four inches onto concrete floor of spent fuel area (May 08);
discovery of inadequate fix of previous years cooling tower collapse (July 08); more cooling tower leaks discovered (September 08);
excess radiation exposure forces temporary evacuation of 12 workers (August 08);
excess radiation exposure forces temporary evacuation of 25 workers (October 08);
discovery of inadequate cooling tower support brackets (October 08);
Atomic Safety and Licensing Board (ASLB) finding of inadequate testing of critical spray nozzles for metal fatigue (November 08);
temporary breakdown of emergency phone system and radio alert system (December 08);
two back-to-back leaks within two days of radioactive water inside the plant, one causing emergency repairs and a 60% reduction of power (January 09);
another leak (not radioactive), this time in switchyard, resulting in 30% power reduction (January 09);
federal report says Entergy finds radioactive contamination of soil surrounding reactor requiring removal of 135,000 cubic feet at a cost of $9.1 million once reactor shuts down (February 09);
January 09 radioactive steam leak continues after two unsuccessful repair attempts (February 09);
Entergy reports another radioactive leak, the third of 2009, and says one of the earlier leaks (after three months of spilling thousands of gallons of radioactive water) was finally fixed a week before this latest leak (April 09).
Another leak is reported in the condenser that cools steam before returning it to the reactor as water (following a similar leak in April 2008 that technicians were unable to find), forcing a planned reduction of power in the next several weeks so that workers can attempt to locate and repair the leak until a new condenser (estimated to cost $100 million) can be installed in 2013 or 2014 (June 09).
radioactive tritium and cobalt found in testing wells surrounding the plant, determined to be entering Connecticut River; source still underterminted and not fixed.